Plant by 6,
6:30 safety meeting with contractor
7-7:30 address any issues that come up as guys go to field
7:30 safety meeting
8:00 walk all jobs down,do some KPAs
9:00 Covid update
9:30-12 evaluate EWOs, sign time sheets, forecast, etc, another walk thru field
1:00 project status updates
2:00 meet with contractors on progress.
3:00 another walk thru field
4:00 review next day plan for critical path jobs with whatever Supt.
4:45 Ivars
Lather, rinse, repeat